59At 230 meters in length and weighing approximately 9,580 tons, THE LINK was elevated to a height of nearly 100 meters in two stages. The first section, weighing around 8,500 tons, was lifted into place between the two towers over a period of 12 days. The remaining cantilever tip, weighing nearly 900 tons, was hoisted and attached during a subsequent four-day procedure.